Deerland Peaking Station Energy Connection (1289)
The Maxim Power Corp. request for system access service to connect its Deerland Peaking Power Station in the Fort Saskatchewan area was cancelled on September 13, 2021.
Cancellation of Needs Identification Document
- Cancellation of the Deerland 13S Substation Modification Needs Identification Document Approval [Posted: Jan. 27, 2022]
Notice
- Cancellation Notice for the Deerland Peaking Station Energy Connection [Posted: Jan. 13, 2022]
Need Overview
- Need for the Deerland Peaking Station Energy Connection in the Fort Saskatchewan area [Posted: Jan. 13, 2022]
Notice of Filing
- Notice of Filing for the Deerland Peaking Station Energy Connection [Posted: Jan. 13, 2022]
Needs Identification Document
- Deerland Peaking Station Energy Connection Needs Identification Document Application [Posted: Jan. 13, 2022]
Appendix A - Connection Assessment
Appendix B - TFO Capital Cost Estimate
Appendix C - AESO Participant Involvement Program
Appendix D - Information Regarding Rule 007, Section 6.1 - NID (13)
Appendix E - AESO Transmission Planning Criteria - Basis and Assumptions
Latest updates
- Cancellation Notice: Deerland Peaking Station Energy Connection