    TVS1 Travers change in maximum capability (MC) notice

    Travers 2 Solar LP is connecting an additional 65 MW to its existing asset, TVS1. Effective March 24, 2022, the approved MC of TVS1 will increase from 400 MW to 465 MW. Please note that the MC change will be reflected on the Current Supply Demand Report effective March 24, 2022.

    Please note that this notification is for MC approvals and that many generation units may initially undergo commissioning and testing activities, or incorporation in phases as applicable, and there may be a period of time before the new generation will output its full MW capability on to the grid.