Blue Bridge Solar Park Connection (2091)
Need for the Blue Bridge Solar Park Connection in the McNeil Area
Blue Bridge Solar Park Limited Partnership (Blue Bridge Solar) has applied to the AESO for transmission system access to connect its proposed Blue Bridge Solar Park (Facility) in the McNeil area. Blue Bridge Solar’s request can be met by the following solution:
- Add one 240 kilovolt (kV) transmission line to connect the Facility to the existing 240 kV transmission line 1002L in a T-tap configuration.
- Add or modify associated equipment as required for the above transmission developments.
Need Overview
- Need for the Blue Bridge Solar Park Connection in the McNeil Area [Sept. 04, 2024]
Latest updates
- Need Overview: Blue Bridge Solar Park Connection