    Nova Solar Project Connection (2378)

    Nova Solar L.P. (Nova) has applied to the Alberta Electric System Operator (AESO) for transmission system access to connect its proposed Nova Solar Project (Facility) in the Carseland area. Nova's request can be met by the following solution:

    • Add one 240 kilovolt (kV) transmission line to connect the Facility to the existing 240 kV transmission line 927L in a T-tap configuration.
    • Add or modify associated equipment as required for the above transmission developments.

    Abbreviated Needs Approval Process: Approval

    The AESO approved the Nova Solar Project Connection under Section 501.3 of the ISO rules, Abbreviated Needs Approval Process.

    Abbreviated Needs Approval Process: Notice of Consideration

    The AESO intends to consider the need for the Nova Solar Project Connection (Project) for approval under Section 501.3 of the ISO rules, Abbreviated Needs Approval Process, (ANAP Rule) on or after October 26, 2022. If stakeholders have any questions or concerns, please contact the AESO before this date.

    The AESO has determined that the Project is eligible for consideration under the ANAP Rule because the following eligibility criteria have been met:

    • Project costs are estimated to be less than $25M and were classified as participant-related in accordance with the ISO tariff;
    • the AESO has completed a participant involvement program (PIP) in accordance with the guidelines in Alberta Utilities Commission Rule 007;
    • the Project is not anticipated to result in significant environmental effects; and
    • No concerns or objections with the need for the Project have been raised. Prior to making its approval decision, the AESO will address additional stakeholder concerns that arise, if any.

    Supporting information about this Project is available in the following documents:

    Market Participant Information

    Need Overview

    Latest updates

    • Nov. 1, 2022 Abbreviated Needs Approval Process: Notice of Approval for the Nova Solar Project
    • Oct. 11, 2022 Abbreviated Needs Approval Process: Notice of Consideration for the Nova Solar Project Connection
    • Aug. 26, 2022 Market Participant Notification for the Nova Solar Project Connection in the Carseland Area
    • Feb. 10, 2022 Need Overview: Nova Solar Project Connection