    AESO Connection Process Schedule Update

    To provide market participants (MPs) with additional flexibility, the AESO is providing a one-time schedule extension to AESO Connection Process timelines in consideration of ongoing engagement on the Restructured Energy Market and other potential framework changes. In summary:

    • MPs in Cluster 1 now have an additional 12 weeks (until Nov. 29, 2024), to provide GUOC evidence or payment and Stage 3 & 4 Security to the TFO, allowing their projects to proceed into Stage 3 of the AESO Connection Process.
      • The project change proposal submission deadline for projects in Cluster 1 is also extended by 12 weeks to Oct. 18, 2024.
    • The closure of the intake window of Cluster 2 is extended by 12 weeks to Oct. 18, 2024.
    • Upon request, the AESO will assess up to a 12-week extension to the stage maximum timeline for projects currently in Stage 3 of the AESO Connection Process.

    Consistent with our previous communications, the AESO is planning to issue the Detailed Assessment Packages for Cluster 1 on June 28, 2024.

    Please click here to read more information about the AESO Connection Process schedule updates.

    Questions regarding the above can be raised to your assigned AESO Project Manager or customer.connections@aeso.ca.