Concord Tilley Partnership (TLE1 Notice)
The effective date of Asset TLE1 has been postponed. The previous effective date was November 27, 2024. The new effective date will be September 10, 2025.
Concord Tilley Partnership is connecting a 24 MW solar generator effective September 10, 2025. The monthly outage and short- term outage graphs will be updated in the normal manner on the AESO’s website based on the information entered in the Energy Trading System. This new capacity will be reflected on the Current Supply & Demand page effective September 10, 2025.
Please note that the date listed on this notice is the date a new asset will be added to the market. However, many generation units may initially undergo commissioning and testing activities, or incorporation in phases as applicable, and there may be a period of time before the new generation will output its full MW capability on to the grid.