Peace Butte Wind Power Project Connection (2467)
Pteragen Canada Inc. (Pteragen Wind) has applied to the AESO for transmission system access to connect its approved Peace Butte Wind Project (Facility) in the Medicine Hat area. Pteragen Wind’s request can be met by the following solution:
- Add one 138 kilovolt (kV) transmission line to connect the Facility to the existing 138 kV transmission line 600L using a T-tap configuration.
- Add or modify associated equipment as required for the above transmission developments.
Needs Identification Document
Peace Butte Wind Power Project Connection Needs Identification Document [Posted: Mar. 31, 2025]
Appendix A - Connection Assessment
Appendix B - Capital Cost Estimate
Appendix C - AESO PIP Summary
Market Participant Notification
- Market Participant Notification for the Peace Butte Wind Power Project in the City of Medicine Hat area [Posted: Nov. 7, 2024]
Need Overview
- Need for the Peace Butte Wind Power Project Connection in the City of Medicine Hat area [Posted: Aug. 21, 2024]
Latest updates
- AESO NID Filed: Peace Butte Wind Power Project Connection
- Market Participant Notification for the Peace Butte Wind Power Project in the City of Medicine Hat area
- Need Overview: Peace Butte Wind Power Project Connection