Eastervale Solar Project Connection (2566)
Eastervale Solar Inc. (ESI) has applied to the AESO for transmission system access to connect its proposed Eastervale Solar Project (Facility) in the Amisk area.
ESI’s request can be met by the following solution:
- Add one 240 kilovolt (kV) transmission line to connect the Facility to the existing 240 kV transmission line 1047L using a T‐tap configuration.
- Add or modify associated equipment as required for the above transmission developments.
Market Participant Notification
- Market Participant Notification for the Eastervale Solar Project Connection [Posted: Dec. 9, 2024]
Need Overview
- Update - Need for the Eastervale Solar Project Connection [Posted: July 2, 2025]
- Need for the Eastervale Solar Project Connection [Posted: Oct. 30, 2024]
Latest updates
- Updated Need Overview: Eastervale Solar Project Connection
- Market Participant Notification for the Eastervale Solar + Storage Project Connection
- Need Overview: Eastervale Solar + Storage Project Connection