Homestead Solar Project Connection (2445)
Kiwetinohk Energy Corp. (Kiwetinohk) has applied to the AESO for transmission system access to connect its approved Homestead Solar Project (Facility) in the Claresholm area. Kiwetinohk’s request can be met by the following solution:
- Add one 240 kilovolt (kV) transmission line to connect the Facility to the existing 240 kV transmission line 1037L in a T-tap configuration.
- Add or modify associated equipment as required for the above transmission developments
Need Overview
- Need for the Homestead Solar Project Connection in the Claresholm area [Posted Nov. 17, 2022]
Latest updates
- Need Overview: Homestead Solar Project Connection