    Oyen 2 Solar Project Connection (2758)

    UK Solar West Ltd. (UK Solar) has applied to the AESO for transmission system access to connect its approved Oyen 2 Solar Project (Facility) in the Oyen area. UK Solar’s request can be met by the following solution:

    • Add a substation, to be designated as North Lanfine 1119S, including three 240 kilovolt (kV) circuit breakers.
    • Connect the proposed North Lanfine 1119S substation to the existing 240 kV transmission line 9L46 using an in-and-out configuration.
    • Add one 240 kV transmission line to connect the Facility to the North Lanfine 1119S substation.
    • Add or modify associated equipment as required for the above transmission developments.

    Market Participant Notification

    The Facility will be connected in the AESO’s Central Planning Region. Market Participants wishing to understand curtailment risk can find congestion information for scenarios that include the Facility in the Central Region Congestion Assessment [Posted: April 22, 2026].

    Need Overview

    Latest updates

    • Apr. 22, 2026 Market Participant Update: Oyen 2 Solar Project Connection
    • Feb. 4, 2026 Need Overview: Oyen 2 Solar Project Connection