Tempest Wind Power Project Connection (2490)
The TransAlta Coaldale Wind (TransAlta) request for system access service to connect its approved Tempest Wind Power Project (Facility) in the Taber area was cancelled on December 1, 2025.
Needs Identification Document Approval Cancellation
Tempest Wind Power Project Connection Needs Identification Document Approval Cancellation [Posted: March 17, 2026]
Notice
- Cancellation Notice for the Tempest Wind Power Project Connection [Posted: March 4, 2026]
Needs Identification Document
Tempest Wind Power Project Connection Needs Identification Document [Posted: Jul. 4, 2024]
Appendix A - Connection Assessment
Appendix B - Capital Cost Estimate
Appendix C - AESO PIP
Notice of Filing
The AESO intends to file the Tempest Wind Power Project Connection Needs Identification Document (NID) application with the Alberta Utilities Commission (AUC) on or after June 27, 2024.
Market Participant Notification
- Market Participant Notification for the Tempest Wind Power Project Connection [Posted: May 29, 2024]
Need Overview
- Need for the Tempest Wind Power Project Connection in the Taber area [Posted: June 14, 2023]
Latest updates
- NID Approval Cancellation filed: Tempest Wind Power Project Connection
- Cancellation Notice: Tempest Wind Power Project Connection
- AESO NID Filed: Tempest Wind Power Project Connection
- Notice of Filing: Tempest Wind Power Project Connection
- Market Participant Notification for the Tempest Wind Power Project Connection
- Need Overview: Tempest Wind Power Project Connection