    Transmission Enhancements in the Northeast Edmonton area (2453)

    EPCOR Distribution & Transmission Inc. (EPCOR) has applied to the AESO for transmission system access to reliably serve a new industrial demand for electricity in the Northeast Edmonton area. EPCOR’s request can be met by the following solution:

    • Add one 240 kilovolt (kV) transmission line to connect a new industrial facility to the existing Clover Bar 987S substation in a radial configuration.
    • Modify the Clover Bar 987S substation, including adding two 240 kV circuit breakers.
    • Add or modify associated equipment as required for the above transmission developments.

    Needs Identification Document

    Transmission Enhancements in the Northeast Edmonton Area Needs Identification Document [Posted: Sept. 29, 2022]

    • Appendix A - Connection Assessment [Posted: Sept. 29, 2022]
    • Appendix B - Capital Cost Estimate [Posted: Sept. 29, 2022]
    • Appendix C - AESO PIP [Posted: Sept. 29, 2022]
    • Appendix D - Distribution Deficiency Report [Posted: Sept. 29, 2022]

    Notice of Filing

    The AESO intends to file the Transmission Enhancements in the Northeast Edmonton area Needs Identification Document (NID) application with the Alberta Utilities Commission (AUC) on or after September 29, 2022.

    Need Overview

    Latest updates

    • Sep. 29, 2022 AESO NID Filed | Transmission Enhancements in the Northeast Edmonton Area
    • Sep. 13, 2022 Notice of Filing: Transmission Enhancements in the Northeast Edmonton area
    • Feb. 8, 2022 Need Overview: Transmission Enhancements in the Northeast Edmonton area