    Recalculated 2012 loss factors

    Loss factors are used to determine the transmission losses charges that apply to system access service under the following rates of the ISO tariff in 2012: 

    • Rate STS, Supply Transmission Service
    • Rate XOS, Export Opportunity Service
    • Rate IOS, Import Opportunity Service
    • Rate DOS, Demand Opportunity Service

     The AESO must recalculate loss factors and losses charges in accordance with Decisions 790-D04-2016 and 790-D06-2017 of the Alberta Utilities Commission in Proceeding 790, Complaints Regarding the ISO Transmission Loss Factor Rule and Loss Factor Methodology. The AESO corrected errors identified in system topologies used in the initial recalculation of Module C loss factors for 2012 and posted the corrected loss factors on September 8, 2021. For more information, see the update posted in the stakeholder engagement section of the loss factor page here. The corrected recalculated 2012 loss factors are provided here: 

    The AESO must provide additional information related to the recalculated loss factors. This additional information is provided here: 

    The initial loss factor postings for the second Module C settlement period, which have been corrected above, remain available below for the interest of stakeholders:

    Actual losses on the transmission system were 2,271 GWh for 2012 and the average loss factor for the transmission system was 3.93% for 2012.