Sunnynook Solar Connection (2464)
Sunnynook Solar Energy Inc. (Sunnynook) has applied to the AESO for transmission system access to connect its proposed Sunnynook Solar project (Facility) in the Hanna area. Sunnynook’s request can be met by the following solution:
- Add one 240 kilovolt (kV) transmission line to connect the Facility to the existing 240 kV transmission line 9L24 using a T-tap configuration.
- Add or modify associated equipment as required for the above transmission developments.
Notice of Filing
The AESO intends to file the Sunnynook Solar Connection Needs Identification Document (NID) application with the Alberta Utilities Commission (AUC) on or after June 13, 2024.
Market Participant Notification
- Market Participant Notification for the Sunnynook Solar Connection in the Hanna area [Posted: May 6, 2024]
Need Overview
- Need for the Sunnynook Solar Connection in the Hanna area [Posted: June 28, 2023]
Needs Identification Document
Sunnynook Solar Connection Needs Identification Document [Posted: Jun. 19, 2024]
Appendix A - Engineering Connection Assessment
Appendix B - Capital Cost Estimates
Appendix C - AESO Participant Involvement Program Summary (PIP)
Latest updates
- AESO NID Filed: Sunnynook Solar Connection
- Notice of Filing: Sunnynook Solar Connection
- Market Participant Notification for the Sunnynook Solar Connection