    Willow Ridge Wind and Battery Project Connection (2503)

    SPWC Development LP, (SPWC), has applied to the AESO for transmission system access to connect its proposed Willow Ridge Wind and Battery Project (the Facility) in the town of Fort MacLeod area. SPWC’s request can be met by the following:

    • Add one 240 kilovolt (kV)transmission line to connect the Facility to the existing 240 kV transmission line 968L in a T-tap configuration.
    • Add or modify associated equipment as required for the above transmission developments.

    Need Overview

    Latest updates

    • May. 29, 2024 Need Overview: Willow Ridge Wind and Battery Project Connection