New Asset Wheatland Wind (WHE1) Notice
Please note that the effective date of Asset WHE1 has been postponed. A new effective date will be communicated once a date is confirmed.
Wheatland Wind Project LP is connecting a 120 MW wind generator effective July 29, 2022. For information purposes, this new capacity will be reflected on the Current Supply & Demand page effective July 29, 2022.
Please note that the date listed on this notice is the date a new asset will be added to the market. However, many generation units may initially undergo commissioning and testing activities, or incorporation in phases as applicable, and there may be a period of time before the new generation will output its full MW capability on to the grid.